Estimated Timeline: We have the construction schedule! Estimated time to open… July 2026. Please fill out the interest form on the home page and we’ll keep you updated!
Electric kiln is delivered! (L&L 2635) Clay is delivered (B-Mix and t2 Clay) Mayco Stoneware glazes ordered (two weeks ETA) Gas kiln ordered (10–12 Month ETA)
Read More
Actually met with the city plan checker to go over details with the plans and get clarity.. should be able to get approval to start actual construction soon... then it…
Read More
Finally! Round Two with the City! Expected to get comments or approval on Feb 27th, 2026. Then we can actually do the build out?
Read More
We are testing the integration of the studio management software into the website. Mostly they show up as classes. Please ignore any of the class information. we are just testing…
Read More
We are currently waiting for the Building Permit process to take place. Then the contractors will be able to start construction. We are currently estimating that will all be done…
Read More
All the Wheels arrived! We now have a mix of Shimpo Whispers, Brents, and Pacifica wheels! They've all been placed in the studio and tested, but will need some wiring…
Read More